California · Code adoption

California adopted codes

Statewide-mandatory (Title 24, California Building Standards Code). Locals may amend with findings filed with CBSC; energy cannot be weakened.

Adopted NEC

Part 3 — CEC 2025 = NEC 2023 + CA amendments

Energy code

Part 6 — 2025 Building Energy Efficiency Standards

Last verified

2026-07-02 · verified

Solar PV, storage & EV

Governing articles
690 / 705 / 706 (PV, interconnection, storage) · 625 (EV supply equipment)
Enforced through
Part 3 — CEC 2025 = NEC 2023 + CA amendments

State-specific solar, storage and EV provisions are covered in the entry below.

California — Code Adoption Summary

Adoption model: Statewide-mandatory (Title 24, California Building Standards Code). Locals may amend with findings filed with CBSC; energy cannot be weakened. Last verified: 2026-07-02 Confidence: verified Primary sources: CA Building Standards Commission — https://www.dgs.ca.gov/BSC · CA Energy Commission (Title 24 Part 6) — https://www.energy.ca.gov · ICC CA codes — https://codes.iccsafe.org/codes/california

Statewide adopted codes — 2025 Title 24 (effective 2026-01-01; triennial cycle)

As of 2026-07-02 the 2025 Title 24 edition is in effect statewide. (The prior 2022 edition ran 2023-01-01 → 2025-12-31.)

Code familyTitle 24 PartAdopted editionNotesSource
BuildingPart 2 — CBC 20252024 IBC base + CA amendmentsdgs.ca.gov/BSC
ResidentialPart 2.5 — CRC 20252024 IRC base"
Electrical (NEC)Part 3 — CEC 2025 = NEC 2023 + CA amendments2022 CEC was NEC 2020; 2025 CEC = NEC 2023Low Voltage Nation / CEC
MechanicalPart 4 — CMC 2025 (UMC-based)IAPMO UMC + CA amend."
PlumbingPart 5 — CPC 2025 (UPC-based)California is a UPC state (IAPMO)"
EnergyPart 6 — 2025 Building Energy Efficiency Standardsstrictest in US; electrification/heat-pump baselineseff. 2026-01-01energy.ca.gov
GreenPart 11 — CALGreen 2025mandatory green buildingdgs.ca.gov/BSC
FirePart 9 — CFC 2025Office of State Fire Marshalosfm.fire.ca.gov

Solar PV / ESS / EV

ItemStatusSource
NEC solar (690/705/706)Via CEC 2025 = NEC 2023 + CA amendmentsCEC 2025
Mandatory solarTitle 24 Part 6 requires PV (and often battery storage) on most new residential + many nonresidential buildingsenergy.ca.gov
SolarAPP+State-backed instant residential PV/storage permitting adopted by many CA jurisdictionssolarapp.gov
EV charger (NEC 625) + EV-readyCALGreen + Part 6 require EV-ready / EVSE parking ratiosCALGreen 2025

Adoption model & precedence

  • Title 24 applies statewide. Local jurisdictions may adopt more-stringent amendments but must file express findings with the California Building Standards Commission; energy (Part 6) cannot be made weaker.
  • Many cities have reach codes (all-electric / stricter energy) filed with the CEC.
  • AHJ = local building department (e.g., LADBS in Los Angeles).

Major cities / counties with their own amendments

JurisdictionCountyOwn code?Key amendmentsBuilding dept.
Los AngelesLATitle 24 + LABC/LAECextensive LA amendments; seismic; LADBSladbs.org
San FranciscoSFTitle 24 + SF amend.SF green/energy reach codessf.gov/dbi
San DiegoSan DiegoTitle 24 + localclimate-action reach codessandiego.gov
San JoseSanta ClaraTitle 24 + all-electric reachelectrification reach codesanjoseca.gov
SacramentoSacramentoTitle 24 + localcityofsacramento.org

AHJ fallback (when local adoption is unverified)

  • State baseline that always applies: 2025 Title 24 (CEC = NEC 2023, CPC = UPC, Part 6 energy, CALGreen).
  • Likely AHJ: city building dept (LADBS, SF DBI, etc.), else county.
  • Action: check for a local reach code / all-electric ordinance and local seismic amendments before design.

Change log

  • 2026-07-02 — created; confirmed 2025 Title 24 in effect (eff. 2026-01-01), CEC 2025 = NEC 2023, CPC = UPC. Prior 2022 CEC = NEC 2020.

Adoption dates move. Confirm the governing edition with the AHJ before issuing for permit — this entry was last checked on 2026-07-02.