Idaho · Code adoption

Idaho adopted codes

Statewide-mandatory floor (Idaho Building Code Board, 3-year legislative adoption cycle); locals may add more-restrictive amendments.

Adopted NEC

NEC 2020

Energy code

IECC 2018

Last verified

2026-07-03 · verified

Solar PV, storage & EV

Governing articles
690 / 705 / 706 (PV, interconnection, storage) · 625 (EV supply equipment)
Enforced through
NEC 2020

Idaho — Code Adoption Summary

Adoption model: Statewide-mandatory floor (Idaho Building Code Board, 3-year legislative adoption cycle); locals may add more-restrictive amendments. Last verified: 2026-07-03 Confidence: verified Primary sources: ID Div. of Occupational & Professional Licenses — https://dbs.idaho.gov · ICC ID

Statewide adopted codes — current (2026)

Code familyAdopted editionNotesSource
Building / Residential2018 I-Codes base (per 2024-era state reference)meltplan.com
Electrical (NEC)NEC 2020up.codes/idaho
Plumbing2017 Idaho State Plumbing Code = UPC-basedIdaho = UPC (not IPC)up.codes/idaho
EnergyIECC 2018"

Adoption model & precedence

  • Codes are statewide; updated every 3 years by the Idaho Legislature as ICC revises, with amendments set by the Idaho Building Code Board.
  • Local jurisdictions (cities/counties) may add their own amendments, generally more restrictive than the state baseline.
  • AHJ = local building department, applying the statewide code + any local amendments.

Major cities / counties

JurisdictionCountyNotesBuilding dept.
BoiseAdastatewide code + local amendments — publishes current-codes pagecityofboise.org
MeridianAdastatewide code + possible local amendmentsmeridiancity.org
NampaCanyonstatewide code + possible local amendmentscityofnampa.us

AHJ fallback (when local adoption is unverified)

  • State baseline (certain): 2018 I-Codes base, NEC 2020, 2017 Idaho Plumbing Code (UPC-based), IECC 2018.
  • Action: confirm any city/county-specific amendments, especially in Boise.

Change log

  • 2026-07-03 — created; verified NEC 2020, UPC-based 2017 Idaho Plumbing Code, IECC 2018, 3-year legislative adoption cycle.

Adoption dates move. Confirm the governing edition with the AHJ before issuing for permit — this entry was last checked on 2026-07-03.