Louisiana · Code adoption

Louisiana adopted codes

Statewide-mandatory (Louisiana State Uniform Construction Code Council — LSUCCC). Law requires review/adoption of the latest NEC within 5 years of publication.

Adopted NEC

NEC 2020 — 2023 NEC under review (next cycle)

Energy code

IECC 2021 + LA amendments

Last verified

2026-07-03 · verified

Solar PV, storage & EV

Governing articles
690 / 705 / 706 (PV, interconnection, storage) · 625 (EV supply equipment)
Enforced through
NEC 2020 — 2023 NEC under review (next cycle)

Louisiana — Code Adoption Summary

Adoption model: Statewide-mandatory (Louisiana State Uniform Construction Code Council — LSUCCC). Law requires review/adoption of the latest NEC within 5 years of publication. Last verified: 2026-07-03 Confidence: verified Primary sources: LSUCCC — https://lsuccc.dps.louisiana.gov/codes-and-standards/ · ICC LA

Statewide adopted codes — current (2026)

Code familyAdopted editionNotesSource
Building2021 IBCLouisiana State Uniform Construction Codelsuccc.dps.louisiana.gov
Residential / Existing / Mechanical / Fuel Gas2021 IRC/IEBC/IMC/IFGC"
Electrical (NEC)NEC 2020 — 2023 NEC under review (next cycle)statutory 5-year review requirementlsuccc.dps.louisiana.gov
PlumbingIPC 2021LA = IPC"
EnergyIECC 2021 + LA amendments"

Adoption model & precedence

  • LSUCCC codes are statewide-mandatory; local jurisdictions enforce with limited amendment authority.
  • Pipeline: 2023 NEC and 2024 ICC-family codes are currently under LSUCCC review — expect an update; confirm effective date before assuming 2020/2021-cycle values remain current for new permits at the time of use.
  • AHJ = local building department, applying the statewide edition.

Major cities / counties (parishes)

JurisdictionParishNotesBuilding dept.
New OrleansOrleansstatewide code + flood/wind provisionsnola.gov
Baton RougeEast Baton Rougestatewide codebrla.gov
ShreveportCaddostatewide codeshreveportla.gov
Lake CharlesCalcasieustatewide codecityoflakecharles.com

AHJ fallback (when local adoption is unverified)

  • State baseline (current): 2021 IBC/IMC/IPC, NEC 2020, IECC 2021.
  • Action: confirm whether the 2023 NEC / 2024 ICC review cycle has been formally adopted yet.

Change log

  • 2026-07-03 — created; verified 2021 I-Codes + NEC 2020 + IECC 2021; flagged 2023 NEC/2024 codes under active LSUCCC review.

Adoption dates move. Confirm the governing edition with the AHJ before issuing for permit — this entry was last checked on 2026-07-03.